

|
|
 |
| |
| How it Works |
| |
| Juneau is fortunate to
have hydroelectric generation for its primary source of
electric power. Our hydro is non-polluting, zero-carbon,
and renewable. In 2007, over 98% of the electric power
generated by AEL&P was produced by hydro. In 2008, even
though we will have more diesel generation than normal, we
will still get 95% of our power from hydro.
The “fuel” for a hydroelectric
generating plant is water. Electric power is generated by
high pressure water in a pipe (penstock) shooting against a
water wheel (turbine) thus spinning the turbine and turning
the electric generator.
Mother Nature provides the
water that fuels the hydro plant in the form of rain and
snow. The water that is used in the plant is stored in
natural reservoirs (like Snettisham) or man-made reservoirs
(like Salmon Creek). This is a good thing, because we can
use water stored in the reservoirs to generate power even
when stream flow is low, such as during dry periods, or
during the winter.
Our reservoir basins act as
large funnels. Precipitation that falls in the basin
eventually flows into the reservoir (except for the small
amount that soaks into the ground or evaporates). Water
flows into the reservoir from rainfall or snowmelt, and
water is taken out of the reservoir for power generation. |
| |
| The Annual Hydro Cycle |
| |
 |
| |
| The above graph helps
illustrate our annual reservoir cycle. Our water year
starts in October. By that time of the year our reservoirs
are at their maximum level, preferably completely full. As
the weather gets colder, the precipitation that falls in the
basin is mostly snow, and so water flow into the reservoir
decreases. During the winter and spring, typically from
November to mid-May, more water is taken out of the
reservoir for power generation than flows in, so the water
level in the reservoir drops.
By mid-May our reservoirs are
at their lowest level. At that time the snowpack that has
been accumulating in the basin begins to melt, stream flow
increases, and more water flows into the reservoir than is
taken out for power generation, so the reservoir level
begins to rise. The reservoir rises due to the melting snow
until roughly August. From August through October we rely
on our fall rains to finish filling the reservoirs. |
| |
| Recent History |
| |
 |
| |
| On the above graph
the green line represents our target reservoir elevation
throughout the year. We call it the “rule curve”. It is
good for the actual water level to be above the rule curve,
because that means we have more water in storage than we
expected. If the actual water level falls below the rule
curve we are in dangerous territory and at a risk for
running out of water in the reservoirs, thus needing to
supplement our hydro with diesel generation. Water year 2006
(black line) was a good
one. We were way above the rule curve all year long. With
the warm, wet weather of December 2005 and January 2006,
reservoir levels remained very high. Even the minimum
elevation in May 2006 was much higher than the rule curve.
The reservoir filled completely, and even overflowed in
September and October 2006.
At the beginning of water
year 2007 (October 2006 -- the blue line) the reservoir was still full, but
as it got cold in November the reservoir level began to
fall. Winter 06-07 was colder than normal. That cold
weather resulted in a record breaking snowfall, but it also
resulted in higher electric loads for heating homes and
businesses. With so much water being taken out of the
reservoir to meet power demands, and so little flowing in
due to low inflow, the reservoir level was actually below
the rule curve by May 2007.
As the record snowpack
melted the reservoir filled rapidly in June and July 2007.
August 2007 was quite dry, and the reservoir didn’t fill as
rapidly, actually falling below the rule curve in August and
staying below through September 2007.
We started water year 2008
(October 2007) below the rule curve, and the reservoir never
filled that fall. With water levels so low, it was clear
that we would need to supplement our hydro generation with
some diesel generation this winter. |
| |
| The
twist |
| |
| Electric
demand in
Juneau
is highest in the winter and lower in the summer.
Our loads have grown to the
point that even with average precipitation, we will not have
enough water in the reservoir to make it through the winter,
and will need to supplement with diesel generation.
But our loads are light enough
in the summer that with average precipitation we will
completely fill and actually spill water from the reservoir.
It sounds odd, but we can run diesel generation in the winter and still
spill from the reservoir in the fall.
This means it will still be
possible to sell surplus energy during the summer, since
spilled water equates to surplus energy. |
| |
| |
Copyright
© 2001-2008 Alaska Electric Light and Power Company
All rights reserved.
|
|