May 24, 2008 --
AEL&P announced today a revised schedule for repair
of the transmission line damaged in the April 16th avalanche. The
new schedule calls for reconnecting to Snettisham by June 8th.
"Several factors have contributed to this
change," said Scott Willis, AEL&P spokesman. "The
contractor on site has worked hard and made good progress.
The original schedule also included a contingency for poor
weather and repair to damaged foundations. We've been
fortunate that damage to the foundations was minimal, and that
we have had very few weather delays."
The two remaining replacement towers were set
in place on Friday and Saturday. Achieving this milestone
has removed some of the uncertainty in the schedule, said
Willis. The next major phase is to pull the conductor
(wire) from tower to tower.
The revised schedule means that the total cost
for diesel during this emergency, and the Emergency Cost of
Power Adjustment effective in mid-June will be lower than
originally anticipated. AEL&P is currently revising its
estimates and will release these revisions early next week.
Contact: Scott Willis
(907) 463-6396 or cell (907) 723-2606