Week 3, 5/3/08 – 5/9/08
Activities
- The site is safe enough for crews to access some
portions.
- The conductor (wire between towers) was tied off
at tower 5/1, the first intact tower on the town side of the
avalanche. This allows a
balanced load on the tower.
- Conductor was also tied off at tower 3/3, the
first intact tower on the Snettisham side of the line.
- Avalanche control work continues.
Natural avalanches continue to come down.
- Conductor was removed from all towers in the
work area.
- It is finally safe enough to access tower 3/5
site. Still 10 to 20 feet of
snow and ice here. Surveyors
marked calculated locations for the three tower foundations and 12
guy anchors which are still buried.
Crews will attempt to find foundations and anchors by setting
burn barrels full of charcoal over the expected spot and letting
them melt down through the snow to the ground.


|