Week 4, 5/10/08 – 5/16/08
Activities
- Damaged parts to towers 4/4 and 4/5 are
repaired.
- Begin using burn barrels
to melt snow at tower 3/5 site.
One of three foundations uncovered so
far and appears usable.
- New insulators installed on tower 4/5.
- Crews finished putting
together tower 4/6 in the staging area.
All three replacement towers are now
complete and on the ground at the staging area waiting for
foundation preparation to be completed.
- Helicopter pad at tower 4/6 rebuilt.
- Additional fuel tanks for heavy lift helicopter
mobilized to Snettisham.


|